For all connections projects there will be some work that must be carried out by SP Energy Networks - these works are deemed to be
non–contestable. The work that can be carried out by ICPs is deemed to be contestable. Below are examples of non–contestable and
contestable works.
- Network design and planning policy
- Equipment and material specification
- Equipment installation and record specification
- Approval of connection design
- Design and determination of POC
- Desired reinforcement upstream of POC
- Consents for upstream reinforcements of assets
- Consents for connections assets for commercial and industrial sites
- Construction/installation of upstream reinforcement assets
- Design of diversion/removal/modification of existing DNO assets
- Work within boundary of any site controlled by DNO
- Connection to existing DNO assets
- Live jointing ( except during the live jointing trial )
- Installation inspection
- Witnessing of commissioning tests
- Additional works resulting from requesting POC on site
- Design of connection downstream from POC to DNO assets
- Consents (way-leaves) for connection assets (Greenfield Housing)
- Construction/installation of connection assets
- Commissioning of connection assets
|